bashar0002
2011-04-06, 10:19 PM
good day
any document about the configuration & how i can use 2G & 3G at the same time , what is the way to configure it , is it by element manager ??
please your help
thanks

wtwat2003
2011-05-26, 07:26 AM
Hi Guys, plz I need the configuration for RBS 6201 2G+3G same time.

what is the instructions to configure it ?

Thank You ,,,

:(

adewijaya
2011-05-26, 07:47 AM
what's main objective in this question? if you have SDR equipment it's must be configured in all in one radio access

bashar0002
2011-05-26, 10:36 PM
good day
i think ti configure 2G + 3G at same time
you have to install a new sub-rack under to original one and deal with it as a separate rack
i think that way & hope to know more form all of you

Yaaqob1982
2011-05-27, 01:22 AM
put the first Du[G/W] in subrack E as a master, then, the Du[G/W] in subrack D as a slavefor making synchronization.
Example: DUG in Subrack E is the Master
DUW in subrack D as a slave
1) you need to create a new IDB for 2G:
standard=3Fan
External=4Fan
define IDB as wizard
arrange the RBS subrack as installed
2)define cabinet product No.
go to Object, Ru [+ click], Active
in the right side you will get RBS6201 [Insert the serial/date/product No.]
3)Configuration, define node parameters:
B1
click add node: chose A5

the Ec cables must connect on the cabinet as follow:

from to
SHU [1A] ASU [A]
SHU [2A] PDU [ECBUS] 2G MASTER
SHU [2B] PDU [ECBUS] 3G SLAVE
SHU [1B] DUG[EC]
SHU [5A] DUW[EC]

now you can install this IDB

For 3G just install the Scripts Automatic, then:
define the following to make synchronization between 2G and 3G
1) Equipment, slot1, Ec port=1
on the right side you will find MO properties
change A0 to A5
2) Equipment, cabinet
define the product/date/serial No.

wtwat2003
2011-05-27, 07:05 AM
put the first Du[G/W] in subrack E as a master, then, the Du[G/W] in subrack D as a slavefor making synchronization.
Example: DUG in Subrack E is the Master
DUW in subrack D as a slave
1) you need to create a new IDB for 2G:
standard=3Fan
External=4Fan
define IDB as wizard
arrange the RBS subrack as installed
2)define cabinet product No.
go to Object, Ru [+ click], Active
in the right side you will get RBS6201 [Insert the serial/date/product No.]
3)Configuration, define node parameters:
B1
click add node: chose A5

the Ec cables must connect on the cabinet as follow:

from to
SHU [1A] ASU [A]
SHU [2A] PDU [ECBUS] 2G MASTER
SHU [2B] PDU [ECBUS] 3G SLAVE
SHU [1B] DUG[EC]
SHU [5A] DUW[EC]

now you can install this IDB

For 3G just install the Scripts Automatic, then:
define the following to make synchronization between 2G and 3G
1) Equipment, slot1, Ec port=1
on the right side you will find MO properties
change A0 to A5
2) Equipment, cabinet
define the product/date/serial No.




Thank Yaqoob (Good Instruction)

WAEL

Yaaqob1982
2011-05-27, 10:13 AM
Welcom wael here

auri_z
2011-08-10, 12:46 AM
Thank Yaqoob (Good Instruction)

WAEL


put the first Du[G/W] in subrack E as a master, then, the Du[G/W] in subrack D as a slavefor making synchronization.
Example: DUG in Subrack E is the Master
DUW in subrack D as a slave
1) you need to create a new IDB for 2G:
standard=3Fan
External=4Fan
define IDB as wizard
arrange the RBS subrack as installed
2)define cabinet product No.
go to Object, Ru [+ click], Active
in the right side you will get RBS6201 [Insert the serial/date/product No.]
3)Configuration, define node parameters:
B1
click add node: chose A5

the Ec cables must connect on the cabinet as follow:

from to
SHU [1A] ASU [A]
SHU [2A] PDU [ECBUS] 2G MASTER
SHU [2B] PDU [ECBUS] 3G SLAVE
SHU [1B] DUG[EC]
SHU [5A] DUW[EC]

now you can install this IDB

For 3G just install the Scripts Automatic, then:
define the following to make synchronization between 2G and 3G
1) Equipment, slot1, Ec port=1
on the right side you will find MO properties
change A0 to A5
2) Equipment, cabinet
define the product/date/serial No.

I think subrack D is change to subrack C
because subrack D for PDU
DUW in subrack C as a slave.

thank you very much for this configuration.it's very usefull

parshav
2011-09-09, 06:34 PM
Dear do u have any video or PPT for 6201 2G BTS commissiong. Pls share or mail me on my mail ID parshavjn@gmail.com

Mctest
2011-09-13, 04:24 AM
put the first Du[G/W] in subrack E as a master, then, the Du[G/W] in subrack D as a slavefor making synchronization.
Example: DUG in Subrack E is the Master
DUW in subrack D as a slave
1) you need to create a new IDB for 2G:
standard=3Fan
External=4Fan
define IDB as wizard
arrange the RBS subrack as installed
2)define cabinet product No.
go to Object, Ru [+ click], Active
in the right side you will get RBS6201 [Insert the serial/date/product No.]
3)Configuration, define node parameters:
B1
click add node: chose A5

the Ec cables must connect on the cabinet as follow:

from to
SHU [1A] ASU [A]
SHU [2A] PDU [ECBUS] 2G MASTER
SHU [2B] PDU [ECBUS] 3G SLAVE
SHU [1B] DUG[EC]
SHU [5A] DUW[EC]

now you can install this IDB

For 3G just install the Scripts Automatic, then:
define the following to make synchronization between 2G and 3G
1) Equipment, slot1, Ec port=1
on the right side you will find MO properties
change A0 to A5
2) Equipment, cabinet
define the product/date/serial No.

Thanks!Could you provide an example with two DUG and one DUW?Where one DUG is master and another slave and DUW is also slave!And it would be great if give as an example with DUW master and DUG slave.

spiderman
2012-01-03, 03:50 PM
put the first Du[G/W] in subrack E as a master, then, the Du[G/W] in subrack D as a slavefor making synchronization.
Example: DUG in Subrack E is the Master
DUW in subrack D as a slave
1) you need to create a new IDB for 2G:
standard=3Fan
External=4Fan
define IDB as wizard
arrange the RBS subrack as installed
2)define cabinet product No.
go to Object, Ru [+ click], Active
in the right side you will get RBS6201 [Insert the serial/date/product No.]
3)Configuration, define node parameters:
B1
click add node: chose A5

the Ec cables must connect on the cabinet as follow:

from to
SHU [1A] ASU [A]
SHU [2A] PDU [ECBUS] 2G MASTER
SHU [2B] PDU [ECBUS] 3G SLAVE
SHU [1B] DUG[EC]
SHU [5A] DUW[EC]

now you can install this IDB

For 3G just install the Scripts Automatic, then:
define the following to make synchronization between 2G and 3G
1) Equipment, slot1, Ec port=1
on the right side you will find MO properties
change A0 to A5
2) Equipment, cabinet
define the product/date/serial No.

Maybe I can add procedure for 3G
For 3G just install the Scripts Automatic, then:
define the following to make synchronization between 2G and 3G

1). Go to containment (MOM Based Menu),

2). Select equipment support function, and change variable to "false"
Note : You have to be make sure false variable cause you choose 2G as a master, so SHU, SCU and Alarm controled by 2G).

3). Select equipment, MO beside left file and view menu, choose add, find mo class "externalnode".
Note : You can find this MO class, only for upgrade Package R3F13 (or R1F13??? Remember me) up to R4D).

4). On the externalnode create 1 as ID, than information only do not change.

5). Until that, From equipment, sort and you will find new mo class externalnode.

6). Select externalnode again, choose MO menu, add again. In the drop down menu choose EC Port. Fill ID with 1 value and Hub Position with B1 (B1 is a EC port cable connected 2G on SHU/SCU),

7). Go to Equipment, select subrack=1, slot1, Ec port=1. On the right side you will find MO properties change it A0 value to A5.
Note : If this correct action, you may see fan sound going more slowly. Or you may see your setting was correct from 2G, with clicked external node menu. You will find correlation name was syncornize with 3G.

8). Go to Equipment again, define the cabinet product/date/serial No.

9). Finishing with save CV as a name CV_ADD_EXT_NODE_2G or etc other.

10). Wish You Luck Bro.

Yaaqob1982
2012-05-05, 05:19 AM
yes, subrack D for PDU
DUW in subrack C or E only
thanks for modification

hsyfcs
2012-08-03, 12:05 PM
thank you very much!
New user can't download document ,I am depressed

Yaaqob1982
2012-08-04, 09:37 PM
Maybe I can add procedure for 3G
For 3G just install the Scripts Automatic, then:
define the following to make synchronization between 2G and 3G

1). Go to containment (MOM Based Menu),

2). Select equipment support function, and change variable to "false"
Note : You have to be make sure false variable cause you choose 2G as a master, so SHU, SCU and Alarm controled by 2G).

3). Select equipment, MO beside left file and view menu, choose add, find mo class "externalnode".
Note : You can find this MO class, only for upgrade Package R3F13 (or R1F13??? Remember me) up to R4D).

4). On the externalnode create 1 as ID, than information only do not change.

5). Until that, From equipment, sort and you will find new mo class externalnode.

6). Select externalnode again, choose MO menu, add again. In the drop down menu choose EC Port. Fill ID with 1 value and Hub Position with B1 (B1 is a EC port cable connected 2G on SHU/SCU),

7). Go to Equipment, select subrack=1, slot1, Ec port=1. On the right side you will find MO properties change it A0 value to A5.
Note : If this correct action, you may see fan sound going more slowly. Or you may see your setting was correct from 2G, with clicked external node menu. You will find correlation name was syncornize with 3G.

8). Go to Equipment again, define the cabinet product/date/serial No.

9). Finishing with save CV as a name CV_ADD_EXT_NODE_2G or etc other.

10). Wish You Luck Bro.

thanks so much for this discription

rama1234
2013-01-01, 04:00 AM
thanks for attach