Can anybody share the step by step commissioning of Minilink R4?
I am new to this equipment.

Thank you in advance

vimcma
2010-09-09, 09:59 PM
Hi there ...

It's the same like R1 R2 and R3 ...

Just difference come with ETU card ... for that You just need to have Ethernet speed tester which will show error's and speed ...

That's all ...

Cost_Reducer
2010-09-10, 05:19 AM
ohhh no, that`s not so easy. What do you like to know? Commisioning of the radio link or setup of the DCN? Please specify your request.
If you need Ethernet traffic you should know if you need a NPU3B with the HighSpeed Bus for switching.
There a many things which you should tell us so we can help you :rolleyes:

vimcma
2010-09-11, 07:10 PM
Thank you for answer ...
I know that NPU3B can handle Layer 3 routing.
I didn't saw commissioning test procedure document at all ...

DCN, X-connection and Radio Part it's not a problem because MMU HW is almost the same ...

Stealth
2010-09-14, 11:07 AM
ohhh no, that`s not so easy. What do you like to know? Commisioning of the radio link or setup of the DCN? Please specify your request.
If you need Ethernet traffic you should know if you need a NPU3B with the HighSpeed Bus for switching.
There a many things which you should tell us so we can help you :rolleyes:

The last time I worked with TN was when it was integrated with MMU (not only high cap LTU).

So, if you dont mind. Please help me with those things that make me so much left behind.

May be I can devide it to: commissioning of the TN, RAU, DCN, and Traffic Management (x connection).

Thank you in advance

milsum
2010-09-14, 05:32 PM
Commisonning includes 5 steps:
1-radio link config(MMU/RAU)
2-Basic NE Config (IP, NE name ..)
3-DCN config (FTP server, PPP link, OSPF, ..)
4-Traffic Routing(Crosss connection for E!, STM1,...)
Some other can also be provided depending on the existing card (Ethernet Bridging/Switching, ATM aggregation ,..)

Stealth
2010-09-14, 07:26 PM
Commisonning includes 5 steps:
1-radio link config(MMU/RAU)
2-Basic NE Config (IP, NE name ..)
3-DCN config (FTP server, PPP link, OSPF, ..)
4-Traffic Routing(Crosss connection for E!, STM1,...)
Some other can also be provided depending on the existing card (Ethernet Bridging/Switching, ATM aggregation ,..)

Do you have the tutorial of the commissioning? I mean the step by step guidance.

I will really appreciate if any of the members could give a favor.

Thank you in advance

Stealth
2010-09-16, 03:22 PM
Got it. I have 2.7 upgrade with SBL 4.3.1.

But the file site >100MB. Any idea of how to share it???

Cost_Reducer
2010-09-16, 04:37 PM
Got it. I have 2.7 upgrade with SBL 4.3.1.

But the file site >100MB. Any idea of how to share it???

It should be already here....try to search in the forum for the software, i mean i had seen this